Opera Energy, via Prabhu Spinning Mills, planned the development of a large-scale Battery Energy Storage System in the state of Kerala. The project is distributed across four substations and required an approach that could respond to challenging land contours and an uneven site shape. Against this backdrop, the engineering effort focused on defining a technically resilient and economically competitive concept that could support a strong bid. Central elements included tailoring the system layout to the site conditions, ensuring consistency across all technical interfaces, and aligning the solution with broader energy storage objectives. The final outcome sought to balance reliable performance with commercial viability. To support this, Fichtner delivered comprehensive pre-bid engineering that shaped the project’s technical and financial foundation.

BESS capacity
Key Facts

Battery Energy Storage Pre-Bid Engineering Services

  • Preparation of layout and single‑line diagram
  • Sizing calculations
  • Technical specifications
  • Preparation of the bill of quantities (BoQ)
  • Cost estimation
  • Financial modeling
  • Engineering for uneven land
  • Bid‑value assessment support
  • 125 MW / 500 MWh BESS capacity
  • 2 cycles 
  • 4 substations (Kerala, India)